The Daily

Friday, November 6, 2026

TransAlta seeks input on potential Alberta data centre · Ottawa commits $32B for First Nations infrastructure · 8 new Calgary building permits

The lead · In the industry · New permits

The lead

TransAlta seeks input on potential Alberta data centre

Open rural land west of Edmonton with nearby utility infrastructure and a field access road, showing the type of setting being considered for a large industrial facility.
Reference photo — not an actual photo of the site.

A large-scale data centre project is taking shape west of Edmonton, with TransAlta, Brookfield and CPP Investments now hearing directly from rural residents in Parkland County.

The partners signed a memorandum of understanding in February to evaluate the Boreal Technology Hub. TransAlta says its teams have been fielding questions as the community-input process continues. The project is still being described as potential, but it would be a major industrial and power-related development if it moves ahead.

For contractors, the location and scale point to the kind of work that would require serious site servicing, civil construction, electrical capacity and building systems. The project partners have not announced a construction award, so this is still at the evaluation and engagement stage.

Journal of Commerce

In the industry

Ottawa commits $32B for First Nations infrastructure

Ottawa is putting $32 billion over 10 years toward repairing, replacing and building First Nations infrastructure, along with another $3 billion for health services.

The commitments are part of the federal budget released Thursday and are aimed at closing an infrastructure gap across First Nations communities. The Assembly of First Nations says the need is greater than the announced funding.

For Alberta contractors, the program could mean more public-sector work in roads, buildings, utilities and health facilities as projects move from funding into procurement.

Daily Commercial News

New permits

8 new Calgary building permits

Issued by the City since the last edition, biggest first. Values are the City's estimated construction cost.

  • $11.5M · Bus terminal alteration

    Greenview Industrial Park · Builder not named

  • $4.27M · Bus terminal alteration

    Southwood · Builder not named

  • $2.5M · New gas bar

    Forest Lawn Industrial · Keller Construction

  • $1.86M · Office alteration

    Downtown Commercial Core · Prime Projects

  • $1.62M · New 5-unit townhouses

    Haysboro · Utopia Construction

  • $1.4M · Retail shop addition

    Sherwood · Builder not named

  • $1.15M · School, sait alteration

    Hillhurst · Builder not named

  • $750K · Retail shop alteration

    Sunridge · Builder not named

The last 7 days

24 building permits, $46.5M in City-estimated construction cost. Busiest communities: Downtown Commercial Core (4).

Most permitted value by builder: Cedarglen Living ($11.4M), Keller Construction ($2.5M), Prime Projects ($1.86M).

Calgary building permits

The network behind the daily

Calgary GCs post commercial work; reviewed subcontractors get asked directly. Free for subs, and we take no cut.