The lead
Bearspaw feeder main work moves to 24-hour shifts

Calgary’s Bearspaw South Feeder Main work is moving into a 24-hour phase this week.
Water demand stayed below 500 million litres for a fifth straight day, with 483 million litres used Saturday and 487 million litres Sunday. That target matters while the City has limited ability to move water through the system during the connection work.
Crews have been draining the existing feeder main and have started excavating at several connection sites. Beginning Thursday, work at the 89th Street N.W. location is scheduled to run 24 hours a day, seven days a week, for about two weeks. Excavation is also set to begin along Parkdale Boulevard.
The work is part of the connection of the new feeder main to Calgary’s water system, with crews also working to maintain water service and firefighting capacity during the shutdown and tie-ins.