The lead
Calgary’s Bearspaw connection work moves into week two

Calgary’s water connection work is moving into its second week, with crews working at three locations as the city manages restrictions across Calgary and nearby communities.
Near the Shaganappi Pump Station, excavation is substantially complete and the tie-in pipe has been exposed ahead of connection work. At 33 Avenue and 89 Street N.W., excavation is complete and crews are preparing to install a new valve. Work is also progressing at the third connection location.
The city reported water use of 473 million litres Tuesday and 475 million litres Wednesday. Keeping daily use below 500 million litres is intended to maintain fire protection, steady water pressure and capacity while the work continues. The city expects the restrictions and construction work to continue for about three more weeks.