The lead
Bearspaw feeder main work moves through winter conditions

The Bearspaw South Feeder Main connection is now halfway through Calgary’s expected four-week Stage 4 water restriction period, with crews working at all three tie-in locations.
Near the Shaganappi Pump Station, tie-in work is continuing and welding is complete on installed pipe segments. At 33 Avenue and 89 Street N.W., crews are installing the final pipe sections connecting the new feeder main and valve chamber to the steel pipe leading to the Bearspaw Water Treatment Plant. Work is continuing 24/7 until the connection is complete.
The City says snow and colder weather are not expected to delay the schedule. Crews are prepared to work through winter conditions and adjust activities as needed. Water use was 482 million litres yesterday, below the 500-million-litre threshold the City says is important while its ability to move water through the system is limited.