Bearspaw connection work reaches halfway point

Calgary’s Bearspaw feeder-main connection work has reached the halfway point in its expected four-week connection window, with crews continuing at all three tie-in locations.
Near the Shaganappi Pump Station, welding is complete on sections of pipe already installed and tie-in work is continuing. At 33 Avenue and 89 Street N.W., crews are installing the final pipe segments linking the new feeder main and valve chamber to the existing system.
The work is continuing through snow and colder weather, with the City saying winter conditions are not expected to delay the timeline. Crews are prepared to work through the conditions and adjust their activities as needed.
Calgary and neighbouring communities used 478 million litres of water yesterday, staying below the 500-million-litre threshold the City says is important while the connection work is underway. Construction continues around the clock until the work is complete.